Zenith Secures a Multi Flare Stack Project
1 Mar 2011
Zenith Structural Access Solutions Limited has won a major project involving eleven different flare stacks and a reinforced concrete chimney. The contract involves multi flare tip replacements and main riser refurbishments together with extensive guy wire replacement and repair. In addition, Zenith will be carrying out extensive repairs to a 150m reinforced concrete chimney. The shutdown is for a forty day period and will see upwards of fifteen operatives on-site from the end of April. “Our worldwide presence continues to be at the forefront of our sales strategy. This particular project in The Middle East demonstrates our logistical capabilities and committment to providing a global service,” comments Colin McCurdy, Managing Director.